London, June 05, 2024 , (Oilandgaspress) ––National Grid is starting work on a new 275kV substation on IAMP to enable new gigafactories and other businesses on the site to plug directly into the electricity transmission network. IAMP is a scheme being brought forward thanks to a joint venture between Sunderland and South Tyneside Councils.
The Hylton Castle substation will provide a new grid connection for Nissan, AESC UK and Sunderland City Council’s ambitious EV36Zero electric vehicle hub at IAMP, which brings together EV manufacture, battery production and a renewable energy microgrid.
Once completed and energised in 2026, Hylton Castle substation will – with its three new 100-tonne supergrid transformers and advanced control systems – reinforce the network in the region and create electricity capacity on site equivalent to powering around half a million homes for a day.
National Grid recently re-routed a kilometre long stretch of pylons and overhead power line to run around the IAMP’s future perimeter, freeing up land for work on the substation and gigafactories to progress on schedule (see video).
Omexom and Taylor Woodrow (OTW) joint venture – part of the VINCI group – has been appointed the contractor to carry out the substation works, with site surveys already underway and construction activity due to start in June.
IAMP spans 150 hectares of land across both Sunderland and South Tyneside local authority areas, and is backed with £42m from the UK government through the Local Growth Fund and North East Local Enterprise Partnership (LEP).