Golding to add second 600 t excavator and 220 t haul truck to Jellinbah East fleet – International Mining

NRW Holdings Limited’s wholly owned subsidiary, Golding Contractors Pty Ltd, has signed a variation to its existing five-year mining services agreement with Jellinbah Mining Pty Ltd at the Jellinbah East coal mine in central Queensland, Australia.

The scope of the variation includes operating and maintaining a second 600-t excavator and 220-t rear dump truck fleet to mine pre-strip overburden, increasing the full scope of the agreement to two 600-t mining fleets.

The variation is valued at approximately A$160 million ($105 million) and will commence in April 2024 using existing owned fleet and supplemented with hire equipment, NRW says.

NRW subsidiary Action Drill & Blast Pty Ltd has also been awarded the following contracts in Queensland:

  • Blasthole drilling services for Batchfire Resources at the Callide coal mine. The contract, valued at circa-A$52 million over five years has commenced and will use a workforce of some 40 personnel;
  • A 12-month extension to supply agreement with Dyno Nobel Asia Pacific Pty Ltd for a Bowen Basin mine valued at A$30 million; and
  • A services agreement involing drilling for a central Queensland mine. This has a contract term of three years on an agreed rates basis with an estimated value of A$28 million.

These contracts will also use existing ADB-owned equipment where applicable, the company said.